Quantcast
Channel: CCIE – IT Certification Success Guaranteed, The Easy Way!
Viewing all articles
Browse latest Browse all 31

[2018-1-NEW] Useful Cisco CCIE 400-151 Dumps CCIE Data Center Written Exam with Latest Version PDF&VCE Youtube Study

$
0
0

What changes have been made to the Cisco 400-151 dumps exam? The CCIE Data Center Written Exam (400-151 CCIE Data Center) exam is a 120 minutes (90 – 110 questions) assessment in pass4itsure that is associated with the CCIE Data Center certification. Useful Cisco CCIE 400-151 dumps CCIE Data Center Written exam with latest version pdf&vce Youtube Study. “CCIE Data Center Written Exam” is the exam name of Pass4itsure Cisco 400-151 dumps test which designed to help candidates prepare for and pass the Cisco 400-151 exam. In these difficult economic times, now organizations are willing to pay to get the right and expert people in the right positions. A professional certification may help increase your income. After the completion of a Cisco https://www.pass4itsure.com/400-151.html dumpsCisco Certified Intenet Expert Data Center candidates can increase professional credibility.

Main objective of Pass4itsure 400-151 CCIE Data Center Preparation material

  • Describe Design
  • Implement and Troubleshoot Data Center Compute Connectivity\nDescribe Design
  • Implement and Troubleshoot Complex Layer 3 Technologies\nDescribe and Integrate Cisco Cloud technologies into existing Data Center infrastructure using sol

[2018-1-NEW Pass4itsure 400-151 Dumps Questions From Google Drive]: https://drive.google.com/open?id=0BwxjZr-ZDwwWbTFibUcwbXBkZms

[2018-1-NEW Pass4itsure 400-201 Dumps Questions From Google Drive]: https://drive.google.com/open?id=0BwxjZr-ZDwwWV2ZxQlJ2OGxkaXc

400-151 dumps

Up to the immediate present 400-151 exam cram(20-28)

QUESTION 20
You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:  You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help offset the risk event?
A. Five days
B. Four days
C. Eleven days
D. Zero
400-151 exam Correct Answer: D
Explanation
Explanation/Reference:
Explanation:
There is no float available for Activity G because it is on the critical path. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options B, A, and C are incorrect. There is no float available for Activity G because it is on the critical path.

QUESTION 21
Beth is the project manager for her organization. Her current project has many deliverables that have been defined at a high level, but the details of the deliverables are still unknown. In her project, Beth is planning in detail only the activities that are most imminent in the project work. This approach to project management planning is known as what?
A. Imminent activity management
B. Rolling wave planning
C. Predecessor-only diagramming
D. Decomposition
Correct Answer: B
Explanation
Explanation/Reference:
Explanation:
Rolling wave planning is a technique to plan and do the most imminent project work before moving onto the details that are far off in the project schedule and project plan. Rolling wave planning is a technique for performing progressive elaboration planning where the work to be accomplished in the near future is
 planned in detail at a low level of the work breakdown structure. The work to be performed within another one or two reporting periods in the near future is planned in detail as work is being completed during the current period.
Answer option D is incorrect. Decomposition is the process of breaking down work packages into the activity list.
Answer options A and C are incorrect. These are not valid project management terms.

QUESTION 22
Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?
A. Scope baseline
B. Organizational process assets
C. WBS
D. Enterprise environmental factors
400-151 dumps Correct Answer: C
Explanation
Explanation/Reference:
Explanation:
According to the PMBOK, Gina will not need the WBS directly, but will rely on the scope baseline. A Work Breakdown Structure (WBS) in project management is a tool that defines a project and groups the project’s discrete work elements in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option A is incorrect. The scope baseline is an input to define the project activities. Answer option
D is incorrect. Enterprise environmental factors are an input to define the project activities.
Answer option B is incorrect. Organizational process assets are an input to define the project activities.

QUESTION 23
You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float. What is the difference between total float and free float?
A. Total float is the amount of time an activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.
B. Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project successors.
C. Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project predecessors.
D. Total float is the amount of time a non-critical activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.
Correct Answer: B
Explanation
Explanation/Reference:
Explanation:
Total float is the time you can delay an activity without delaying the project end date, whereas free float is on each activity and does not affect the early start date of successor activities. Float, also called slack, is
  the amount of time an activity can be delayed without affecting any subsequent activities. There are two types of floats available: Free Float: It is the amount of time a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities. Total Float: It is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating schedule constraint. Float is calculated by using the critical path method technique. Answer options C, A, and D are incorrect. These are not accurate definitions of free float and total float.

QUESTION 24
John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:
Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?
A. Zero
B. One
C. Four
D. Five
400-151 pdf Correct Answer: A
Explanation
Explanation/Reference:
Explanation:
The path of ABEHJ will take 22 days to complete and cannot exceed 28 days or else the project will be late. If Activity B takes four additional days and Activity E takes two additional days, this adds (4+2= 6) six days to the path, bringing the path’s duration to exactly (22+6 = 28) days. There is no available float left for Activity D or H. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options B, C, and D are incorrect. There is no float available because the path’s duration has increased to 28 days.

QUESTION 25
Ben is the project manager for his organization. His project has 26 stakeholders this week and will have five additional stakeholders next week. How many more communication channels will Ben’s project have next week?
A. 140

B. 10
C. 325
D. 5
Correct Answer: A
Explanation
Explanation/Reference:
Explanation:
Ben’s project will have 140 more communication channels because of the five additional stakeholders. To solve the question, you will need to find the current stakeholder communication channels first, which is (26*25)/2= 325, and then find the difference of the number of channels for the five additional stakeholders. You can use the formula of N(N-1), where N is the number of stakeholders. In this example, the formula would read: Total number of communication channels that Ben will have next = ((31*30)/2)-((26*25)/2 =140
Answer option D is incorrect. Five is the number of additional stakeholders. Answer option B is incorrect. 10 is the number of communication channels among just five stakeholders. Answer option C is incorrect. 325 is the number of current communication channels.

QUESTION 26
You are the project manager for your company. You are working with the activities defined in the figure below. What will happen to your project if Activity F takes five additional days to complete than what was expected?
A. Your project’s critical path will shift to ACFI.
B. Your project will be late by five days.
C. Your project can still complete on time as float is available on Activity I.
D. Your project will now have two critical paths.
400-151 vce Correct Answer: B
Explanation
Explanation/Reference:
Explanation:
Activity F is on the critical path of ACFHK of 30 days. By adding five additional days to Activity F, the
  project will now take 35 days to complete. Answer options C, A, and D are incorrect. These are not the valid answers.

QUESTION 27
You are the project manager for your organization. You need the oak cabinets for your project delivered by December 1 in order to install the floors around the oak cabinets by December 15. Your company’s procurement office generally takes 45 days to complete procurement orders. Based on this information, how should you schedule the lead time for the cabinet delivery?
A. Cabinet procurement December 1, plus 45 days lead time
B. Cabinet procurement November 15
C. Cabinet procurement December 1, minus 45 days lead time
D. Cabinet procurement December 15 minus 45 days lead time
Correct Answer: C
Explanation
Explanation/Reference:
Explanation:
The cabinet procurement and delivery must be completed by December 1. By scheduling the activity to finish on December 1 with minus 45 days lead time for procurement, the cabinets will arrive by the needed date.
Answer option A is incorrect. Lead time is always negative time, lag time is positive time. This choice would cause the cabinets to not arrive until 45 days after December 1. Answer option D is incorrect. This choice would cause the cabinets to arrive on December 15 when the floors are to be installed.
Answer option B is incorrect. This choice is not the best answer because it does not necessarily account for holidays, weekends, or other factors in the project calendar. By scheduling the cabinet for December 1 and working backwards through lead time, the project’s PMIS will account for these breaks in the project work.

QUESTION 28
Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget. What is the to-complete performance index for this project?
A. 0.98
B. -$16,677
C. 1.07
D. 0.94
400-151 exam Correct Answer: C
Explanation
Explanation/Reference:
Explanation:
The to-complete performance index can be found by using the formula (BAC-EV)/(BAC-AC) for a value of 1.07. The higher the value is from 1, the less likely the project will meet the BAC. To-complete Performance Index (TCPI) is the measured projection of the anticipated performance required to achieve either the BAC or the EAC. TCPI indicates the future required cost efficiency needed to achieve a target EAC (Estimate At Complete).Once approved, the EAC supersedes the BAC as the cost performance goal. Any significant difference between TCPI and the CPI needed to meet the EAC should be accounted for by management in their forecast of the final cost. The formula for TCPI is as follows:
TCPI = {(BAC-EV)/(BAC-AC)}
Answer option A is incorrect. 0.98 is the project’s cost performance index. Answer option D is incorrect. This is the project’s schedule performance index. Answer option B is incorrect. -$16,667 is the project’s variance at completion.

 

400-151 dumps

After the completion of Cisco Certified Intenet Expert Data Center 400-151 dumps you can realize maximum advantages from a wide range of expertise. “CCIE Data Center Written Exam”, also known as 400-151 exam, is a Cisco certification which covers all the knowledge points of the real Cisco exam. Pass4itsure Cisco 400-151 dumps exam questions answers are updated (408 Q&As) are verified by experts. The associated certifications of https://www.pass4itsure.com/400-151.html dumps is CCIE Data Center.

Read More Youtube: https://youtu.be/1VfMp20O3ao

 

The post [2018-1-NEW] Useful Cisco CCIE 400-151 Dumps CCIE Data Center Written Exam with Latest Version PDF&VCE Youtube Study appeared first on IT Certification Success Guaranteed, The Easy Way!.


Viewing all articles
Browse latest Browse all 31

Trending Articles